Friday 14 June 2013

Day 50 (68) - Interlull. Not much going on


This week has been a quiet one and we're not due to have any trades on site until next week. This has been primarily due to a delay from the brick suppliers but also because the weather has been somewhat unpredictable. 

Where progress has been made though is on the side extension as we now have the roof framework up together with the soffit and fascia. 


Below is a close up of the framework as seen from roof level. 


Next week we will have delivery of the final steel beam which will go in the roof space to support the new gable end roof. We will also have the bricked in to complete the remaining brickwork for the rear gable end and the side gable end. We should also see the roofers on site to complete the structure with the laying of the roof tiles. 